Renovation Projects

District Overview
Of the four school buildings, three of them have various components and systems that have exceeded their projected life-cycles.

Alloway Creek Intermediate School was completed in 2003, has been well maintained, and with continued maintenance should not provide any major issues in the foreseeable future. The Intermediate School houses the District Administration Office.

The High School was originally constructed in 1960 and has received two substantial additions since 1993. The structure continues to function as designed, however various systems and components will require attention in the foreseeable future. Upgraded/new systems and replaced components should provide more cost-effective operations and extended life.

Maple Avenue Middle School was originally constructed in 1932 with substantial additions in 1973 and 1991. The building still utilizes a number of components from the 1932 construction including some wood structure and egress components in the three story portion. The Middle School contains the District's preparation kitchen.  

Rolling Acres Elementary School was originally constructed in 1952 and received substantial additions in 1972 and 1990. All major components and systems are 20 plus years of age and should be thoroughly inspected for potential pending issues. There are significant accessibility and acoustical issues in the 1972 portion of the building, including the gymnasium that is only accessible from stair towers.

The Transportation and Maintenance Building was constructed in 2001 and is fully utilized. Several efficiency, safety and operational issues have been identified and should be considered as the opportunities are presented.

The Stadium, Concession Stand, and Toilet Facilities have served the District for many years with limited upgrades. Consequently, there are a number of accessibility and safety issues that will need to be addressed in immediate future.

LASD Property with Wet Areas and Topographical Views

Littlestown Area School District Aerial Image (Overall Campus)

Littlestown Area School District Aerial Image (Overall Campus)

Middle School/High School Renovations/Additions Building Project - 2023-2025

Concept rendering of MS/HS Building

Click on below link to find all information on the MS/HS Project:

MS/HS Project Timeline of Events, Presentations, and Approvals

Aerial Views of Stadium Complex May 2019 Completion

April 2019

March 12, 2019

New Stadium Pre-Bid - November 9, 2017

Master Plan for Athletic Facility Improvements - June 2017

Campus Improvements Presentation - February 2017

Extra Curricular Update - October 2016

Building Project Update - May 9, 2016

4th & 5th Grade Move for 2016-2017 - Q & A

Front Facade of the new Alloway Creek Elementary School

Updated Site Plan Graphic for Alloway Creek Elementary School Play Areas - 1-18-16

Act 34 Public Hearing Presentation

Building Project Update - January 2016

Building Renovation Update - August 2015

Building Renovation Update - June 2015

More Info

RA Before Pictures

MA Before Pictures

Building Projects
Calendar

ALLOWAY CREEK ELEMENTARY SCHOOL

BEGIN/SUBMISSION

COMPLETION DATE

Overall Proposed Schedule

May 2015

August 2017

PDE PlanCon A & B Review

August 4, 2015

PDE PlanCon Process (Act 34 Hearing)

August 4, 2015

End 2017

Code Review/L&I Plans & Existing Info (Survey)

July 2015

March 2016

Anticipated Land Development (6 to 9 months)

Existing Building Surveys & Staff Meetings

Late August 2015

March 2016

Out to Bid

March/April 2015

Start of Construction

May/June 2016

Project Substantially Complete

August 2017

STADIUM/ATHLETIC IMPROVEMENTS

BEGIN/SUBMISSION

COMPLETION DATE

Overall Proposed Schedule

June 2015

August 2017

Anticipated Land Development (6 to 9 months)

Naming Rights/Donations

March 2016

Out to Bid

March 2017

Start of Construction

May 2017

Project Substantially Complete

August 2017

HIGH SCHOOL SELECTIVE REROOFING

BEGIN/SUBMISSION

COMPLETION DATE

Athletic Meeting

August 27, 2015

First Advertisement to Bid

August 27, 2015

Second Advertisement to Bid

August 30, 2015

Drawings/Specifications Available

August 31, 2015

Pre-bid at Maintenance Bldg and Tour Roof at 1:30 PM

September 3, 2015

Third Advertisement to Bid

September 6, 2015

Receipt of Bids in District Office at 2:00 PM

September 10, 2015

Begin Roof Replacement Construction

October 9, 2015

November 20, 2015

Littlestown Area School District Meeting Schedule

DAY

DAY OF WEEK

MEETING TYPE

LOCATION/TIME

April 13, 2015

Monday

Board Work Session; CRA to proceed with Feasibility Study

DO / 7 PM

April 15, 2015

Wednesday

CRA Design Team Meeting; Review Feasibility Study and Contact Engineers

CRA Only

April 20, 2015

Monday

Board Voting Meeting

DO / 7 PM

April 24, 2015

Friday

Design Team Kick-Off Meeting; Discuss LASD Feasibility Scope, Budget and Schedule and Review To Do & Needs List

CRA Office TBD

Wk of April 27, 2015

All Week

Tour of District Buildings and Discuss Concerns/Needs

TBD

May 1, 2015

Friday

Design Team Meeting; Review Bldg Options and Scope; Review Rough Estimates; Review To Do & Needs List

DO / 1-3 PM

May 8, 2015

Friday

Design Team Meeting; Refine Bldg Options, Review Preliminary Estimates, Review To Do and Needs List

CRA / 1-3 PM

May 11, 2015

Monday

Board Work Session; Update/Status

DO / 7 PM

May 14, 2015

Thursday

Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List

TBD / 1-3 PM

May 18, 2015

Monday

Board Voting Meeting

DO / 7 PM

May 21, 2015

Thursday

Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List

TBD / 1-3 PM

May 28, 2015

Thursday

Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List

TBD / 1-3 PM

June 1, 2015

Monday

Board Work Session; Discuss Project Options and Ideas

DO / 6:30 PM

June 2, 2015

Tuesday

Voluntary Employee Meeting to Provide Input and Receive Updates for Building and Extra-Curricular Renovations

MA Aud / 3:45

June 4, 2015

Thursday

Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List

TBD / 1-3 PM

June 8, 2015

Monday

Town Hall Meeting; Provide Input and Receive Updates for Building and Extra-Curricular renovations

MA Aud. 6 PM

June 11, 2015

Thursday

Design Team Meeting/ Review Feasibility Study Progress, Review To Do and Needs List

TBD / 1-3 PM

June 15, 2015

Monday

Board Work Session; Update review draft of amended Feasibility Study

DO / 6 PM

June 16, 2015

Tuesday

Voluntary Employee Meeting to provide input and receive updates for building and extra-curricular renovations

RA Cafe/4 PM

June 17, 2015

Wednesday

Town Hall Meeting; Provide input and receive updates for building and extra-curricular renovations

MA Aud  6 PM

June 18, 2015

Thursday

Design Team Meeting; Final Review of Feasibility Study

CRA / 1-3 PM

June 22, 2015

Monday

Board Voting Meeting; Approve amended Feasibility Study

DO / 7 PM