Renovation Projects
District Overview
Of the four school buildings, three of them have various components and systems that have exceeded their projected life-cycles.
Alloway Creek Intermediate School was completed in 2003, has been well maintained, and with continued maintenance should not provide any major issues in the foreseeable future. The Intermediate School houses the District Administration Office.
The High School was originally constructed in 1960 and has received two substantial additions since 1993. The structure continues to function as designed, however various systems and components will require attention in the foreseeable future. Upgraded/new systems and replaced components should provide more cost-effective operations and extended life.
Maple Avenue Middle School was originally constructed in 1932 with substantial additions in 1973 and 1991. The building still utilizes a number of components from the 1932 construction including some wood structure and egress components in the three story portion. The Middle School contains the District's preparation kitchen.
Rolling Acres Elementary School was originally constructed in 1952 and received substantial additions in 1972 and 1990. All major components and systems are 20 plus years of age and should be thoroughly inspected for potential pending issues. There are significant accessibility and acoustical issues in the 1972 portion of the building, including the gymnasium that is only accessible from stair towers.
The Transportation and Maintenance Building was constructed in 2001 and is fully utilized. Several efficiency, safety and operational issues have been identified and should be considered as the opportunities are presented.
The Stadium, Concession Stand, and Toilet Facilities have served the District for many years with limited upgrades. Consequently, there are a number of accessibility and safety issues that will need to be addressed in immediate future.
LASD Property with Wet Areas and Topographical Views
Littlestown Area School District Aerial Image (Overall Campus)
Middle School/High School Renovations/Additions Building Project - 2023-2025
Click on below link to find all information on the MS/HS Project:
MS/HS Project Timeline of Events, Presentations, and Approvals
Aerial Views of Stadium Complex May 2019 Completion
April 2019
March 12, 2019
New Stadium Pre-Bid - November 9, 2017
Master Plan for Athletic Facility Improvements - June 2017
Campus Improvements Presentation - February 2017
Press Release: Safe Fields Alliance and Synthetic Turf Council Response to EPA Status Report
District Campus Improvements for Athletic Facility Upgrades
Extra Curricular Update - October 2016
Building Project Update - May 9, 2016
4th & 5th Grade Move for 2016-2017 - Q & A
Front Facade of the new Alloway Creek Elementary School
Updated Site Plan Graphic for Alloway Creek Elementary School Play Areas - 1-18-16
Act 34 Public Hearing Presentation
Building Project Update - January 2016
Building Renovation Update - August 2015
Building Renovation Update - June 2015
RA Before Pictures
MA Before Pictures
Building Projects
Calendar
ALLOWAY CREEK ELEMENTARY SCHOOL | BEGIN/SUBMISSION | COMPLETION DATE |
---|---|---|
Overall Proposed Schedule | May 2015 | August 2017 |
PDE PlanCon A & B Review | August 4, 2015 | |
PDE PlanCon Process (Act 34 Hearing) | August 4, 2015 | End 2017 |
Code Review/L&I Plans & Existing Info (Survey) | July 2015 | March 2016 |
Anticipated Land Development (6 to 9 months) | ||
Existing Building Surveys & Staff Meetings | Late August 2015 | March 2016 |
Out to Bid | March/April 2015 | |
Start of Construction | May/June 2016 | |
Project Substantially Complete | August 2017 | |
STADIUM/ATHLETIC IMPROVEMENTS | BEGIN/SUBMISSION | COMPLETION DATE |
Overall Proposed Schedule | June 2015 | August 2017 |
Anticipated Land Development (6 to 9 months) | ||
Naming Rights/Donations | March 2016 | |
Out to Bid | March 2017 | |
Start of Construction | May 2017 | |
Project Substantially Complete | August 2017 | |
HIGH SCHOOL SELECTIVE REROOFING | BEGIN/SUBMISSION | COMPLETION DATE |
Athletic Meeting | August 27, 2015 | |
First Advertisement to Bid | August 27, 2015 | |
Second Advertisement to Bid | August 30, 2015 | |
Drawings/Specifications Available | August 31, 2015 | |
Pre-bid at Maintenance Bldg and Tour Roof at 1:30 PM | September 3, 2015 | |
Third Advertisement to Bid | September 6, 2015 | |
Receipt of Bids in District Office at 2:00 PM | September 10, 2015 | |
Begin Roof Replacement Construction | October 9, 2015 | November 20, 2015 |
Littlestown Area School District Meeting Schedule
DAY | DAY OF WEEK | MEETING TYPE | LOCATION/TIME |
---|---|---|---|
April 13, 2015 | Monday | Board Work Session; CRA to proceed with Feasibility Study | DO / 7 PM |
April 15, 2015 | Wednesday | CRA Design Team Meeting; Review Feasibility Study and Contact Engineers | CRA Only |
April 20, 2015 | Monday | Board Voting Meeting | DO / 7 PM |
April 24, 2015 | Friday | Design Team Kick-Off Meeting; Discuss LASD Feasibility Scope, Budget and Schedule and Review To Do & Needs List | CRA Office TBD |
Wk of April 27, 2015 | All Week | Tour of District Buildings and Discuss Concerns/Needs | TBD |
May 1, 2015 | Friday | Design Team Meeting; Review Bldg Options and Scope; Review Rough Estimates; Review To Do & Needs List | DO / 1-3 PM |
May 8, 2015 | Friday | Design Team Meeting; Refine Bldg Options, Review Preliminary Estimates, Review To Do and Needs List | CRA / 1-3 PM |
May 11, 2015 | Monday | Board Work Session; Update/Status | DO / 7 PM |
May 14, 2015 | Thursday | Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List | TBD / 1-3 PM |
May 18, 2015 | Monday | Board Voting Meeting | DO / 7 PM |
May 21, 2015 | Thursday | Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List | TBD / 1-3 PM |
May 28, 2015 | Thursday | Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List | TBD / 1-3 PM |
June 1, 2015 | Monday | Board Work Session; Discuss Project Options and Ideas | DO / 6:30 PM |
June 2, 2015 | Tuesday | Voluntary Employee Meeting to Provide Input and Receive Updates for Building and Extra-Curricular Renovations | MA Aud / 3:45 |
June 4, 2015 | Thursday | Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List | TBD / 1-3 PM |
June 8, 2015 | Monday | Town Hall Meeting; Provide Input and Receive Updates for Building and Extra-Curricular renovations | MA Aud. 6 PM |
June 11, 2015 | Thursday | Design Team Meeting/ Review Feasibility Study Progress, Review To Do and Needs List | TBD / 1-3 PM |
June 15, 2015 | Monday | Board Work Session; Update review draft of amended Feasibility Study | DO / 6 PM |
June 16, 2015 | Tuesday | Voluntary Employee Meeting to provide input and receive updates for building and extra-curricular renovations | RA Cafe/4 PM |
June 17, 2015 | Wednesday | Town Hall Meeting; Provide input and receive updates for building and extra-curricular renovations | MA Aud 6 PM |
June 18, 2015 | Thursday | Design Team Meeting; Final Review of Feasibility Study | CRA / 1-3 PM |
June 22, 2015 | Monday | Board Voting Meeting; Approve amended Feasibility Study | DO / 7 PM |